Bolted Flange Prying in Fired Heaters and Supporting Structures – Part 2

Structural Analysis Concepts for Beginner Mechanical Engineers – Part 2

 
This series of posts introduces concepts that are missing from undergraduate (Mechanical Engineering) curricula but are essential to the safe design of industrial equipment and supporting structures. The first part in the series concerned the beam failure mode of Lateral Torsional Buckling. The second part covers a narrow but critical topic: bolted flange design due to prying forces.
 
Like the previous post, this is just an introduction to the concept. This article is not sufficiently in depth to provide competence in tension connection design.
 
Most machine design courses and textbooks cover bolted connections. They cover bolt group shear connections, some cover bolt groups in tension, but very few address checking the flanges that the bolts are trying to hold together. When a bolt group connection is resisting a load in tension, most machine design textbooks (e.g. Shigley) treat the plates as perfectly rigid. Therefore, the tension is transferred perfectly to the bolts. While this is a fine teaching method, perfect rigidity of the flanges cannot always be assumed.
 
Ductility is one of steel’s most advantageous characteristics. In fact, in most cases, a design that eliminated all deflection would seem overly conservative and wasteful. However, this ductility can cause unintended consequences, one of which can be found in bolted tension connections. In this type of connection an additional load is applied to a bolt from the prying action of a deflected flange. This prying can occur in any tension connection where the applied load is not coincident with the axis of the bolt. Bolt groups in tension see this type of loading in nearly all applications and therefore are subject to prying forces.
 
In the 15th edition of the AISC SCM the prying equations start at Part 9 Page 10. The manual states “Prying action is a phenomenon (in bolted construction only, and only in connections with tensile bolt forces) whereby the deformation of a connecting element under a tensile force increases the tensile in the bolt above that due to the direct tensile force alone”.
 
In this article, bolted elements are referred to as the “steel” and could be wide flange beams, channels, angles, or weldments of steel plate. If the basic configuration shown in Figure 1 and 2 are maintained, the concepts apply.
 
As shown in Figure 1, if the load on the web/leg is large enough to cause deflection in the flange, this can act as a lever arm about point “A” and cause a prying force under the bolt head. This prying action increases the force on the bolt above what is calculated by statics. This additional load must be calculated and accounted for or eliminated.
 
Figure 1
 
There are two ways of looking at this problem and how it can affect the bolt. First is to make the flange strong (thick) enough to avoid the prying action altogether. Secondly, we can leave the flange as designed and calculate this additional force so that it can be applied to the bolt and checked against the allowable load of the bolt.
 
Figure 2
 
For some projects, the deflection associated with prying might be acceptable. For fired heaters, air exchangers, fans, duct work and the other equipment we design/connect to in the refining industry, it is common to design the flange for no prying action. Designing for the no prying condition ensures that no flue gas or combustion air leakage at the bolted joint occurs. While deflection at these bolted connections would not impact the structural safety of the equipment, eliminating tramp air into the combustion system is always a priority in process equipment. With that in mind this article will focus on the “no prying” procedure as laid out in the AISC SCM. The ASD equations will be presented, but the concepts are the same for LRFD.
From the SCM, Equation 9-17b is arranged to give the required flange thickness in order to reduce the prying force to “essentially zero.”
Let’s break down this equation. The easiest way is to start with a tension force (T) applied through the center of the leg, this force creates a bending moment about point “A” (Figure 1). The maximum moment the flange could resist would normally be determined by the plastic moment of inertia multiplied by the yield strength, and then either Ø or Ω applied, M = Z*Fy/Ω. As stated on page 9-10 the material’s tensile strength is used in this equation because it aligns better with the experimental data collected.
 
The plastic moment of inertia for a rectangle around the center of gravity is:
Putting this together we get:
Solving for “d” or thickness, we get equation 9-17 from the AISC SCM.
 
Satisfying this equation gives a flange thickness that will resist any significant deflection that could cause the prying effect.
 
A note on the variable “p”, as noted on page 9-12. It can be taken as 3.5*b, but should not exceed the bolt spacing. This guidance was not in the previous editions of the SCM and may be new to those using older editions. Also new in the 15th edition is the form of equation 9-17. Previously the “4” and Ω were combined to read 6.66. The new version, which is numerically the same, is much clearer.
 
The technique above is commonly used for sizing steel members, but there is another way to look at equations in the SCM procedure.
 
Consider a hypothetical situation where you have a beam that is already sized and built, and the customer wants to hang piping from it (because they always want to hang piping from it). The piping support connection is often a pipe hanger hanging from the beam flange or something similar. The additional loads on the member are typically small enough to not require any changes to the beam size, the end connections, or the overall structure layout but should be checked. The local stresses on the beam also need to be considered. The flange prying procedure can be used to see how many bolt pairs would be required to hold the load with the existing flange size. The load would be divided by the allowable force on the flange at each bolt. This number is rounded up to the nearest even number. This is how many bolts the existing flange requires to support the intended load. This number of bolts must also be large enough for the bolt themselves to support the load.
 
If the “no prying” configuration is not required, the loading on the bolt with the effects of prying action can be determined by equation 9-27. If the available strength of the bolt is not sufficient to carry the load, more bolts must be added. Adding more bolts will reduce the tension per bolt and reduce the prying force experienced by the bolt.
 
I hope this introduction to the concept of prying at bolted connections helps you design connections that are safer and more efficient.

A few notes:

  • Gussets between bolt holes can be used to stiffen the flange. This is not covered here or in the Manual. A source of information that might help is “A Yield Line Component Method for Bolted Flange Connections” by Bo Doswell.
  • CICIND has alternative equations that might be helpful.
  • While this is not apparent from Figure 9-4, the distance b’ (from the center of the angle leg to the edge of the bolt hole) as the moment arm on an angle is based on the assumption that the actual connection is a back to back angle. If the connection is a single angle (like on ductwork flange connection) it is suggested that the b’ dimension be at least to the outside of the angle. Suggested reading is Modern Steel Construction “Steel Interchange” February 2015.
  • A couple of additional suggested articles: “A Quick Look at Prying” and “A Slightly Longer Look at Prying”, both by Caro Lini. Of course, chapter 9 of the SCM should be read as well.

References

American Institute of Steel Construction. (2017). Steel Construction Manual . Chicago: American Institute of Steel Construction.
Please fill out the form below and we will be in contact as soon as possible.
GET IN TOUCH
Name(Required)
This field is for validation purposes and should be left unchanged.
Please fill out the form below and we will be in contact as soon as possible.
GET IN TOUCH
Name(Required)
This field is for validation purposes and should be left unchanged.
ERWIN PLATVOET
As CTO of XRG, Erwin is a true innovator, whose career spans more than three decades in heat transfer and combustion industries. Erwin is a graduate of Twente University in the Netherlands with a MS in Chemical Engineering. Erwin has served the industry around the globe in a variety of roles including Research and Development Engineer, Cracking Furnace Specialist, and Director of Engineering, and now CTO. Erwin holds eight patents in fired heat transfer and emissions control technology, has published numerous papers, and co-authored the John Zink Combustion handbook and Industrial Combustion Testing book. Erwin has been an active member of the API 560 and API 535 subcommittees and taken an active role in revising these standards.
BAILEY HENDRIX
Bailey graduated from Oklahoma State University with a Bachelor of Science in Mechanical Engineering. Upon graduation, she joined the private sector as an Applications Engineer in Tulsa, OK at a local combustion company where she managed the sales activities for the process burner refining market. She quickly accelerated her career, becoming the Refining Account Manager responsible for all business development and sales of process burners in North and South America. Her strong leadership skills and interpersonal qualities led her to a position as the Western Hemisphere Sales Director for the process burner business, leading a group of sales engineers in the areas of new equipment, retrofits and burner management systems. Her financial and commercial acumen drives the success of XRG Technologies’ business development.
ALLEN BURRIS
Allen’s background includes 10 years of experience in designing and selling process burners. Allen is a graduate of Oklahoma State University with a BS in Mechanical Engineering and is a licensed professional mechanical engineer in the State of Oklahoma. His knowledge and superior customer focus led him to a career change to process design, custom-engineered fired heater sales, and associated sub-systems for the petrochemical, refining and NGL industries. With more than two decades of experience in the combustion and fired heater industry, Allen has what it takes to overcome challenges associated with complex projects and possesses.
TIM WEBSTER
With over 25 years of experience in the combustion industry, Tim brings a wealth of industry experience and technical expertise to XRG. Tim graduated with a Bachelor of Science in Mechanical Engineering from San Jose State University and received a Master of Engineering from the University of Wisconsin. Tim began his career engineering custom combustion systems for a wide range of applications including boilers, heaters, furnaces, kilns, and incinerators. Tim is a licensed professional mechanical engineer in the states of California, Texas, Louisiana and Oklahoma, has authored numerous articles and papers, and has co-authored several combustion handbooks.
matt martin
As the Lead Scientist at XRG, Matt has over 30 years of experience in the combustion industry. He specializes in CFD of fired equipment, including UOP platforming heaters, burners in process heaters, thermal oxidizers and flares with over 300 simulations of installed, field-proven equipment. Matt received a Bachelor of Science in Computer Science with a minor in Mathematics from the University of Tulsa. He has written numerous publications, is listed as inventor or co-inventor on 27 patents and was awarded the title of Honeywell Fellow in 2011 for technical excellence and leadership.
gina briggs
Gina is a native Oklahoman and attended the University of Tulsa, graduating with a BSBA in Accounting. She is a Certified Public Accountant and Chartered Global Management Accountant. Gina began her career with the Tulsa office of Deloitte Haskins and Sells, providing audit and tax services. Since leaving Deloitte, she has held CFO positions with privately held companies in the manufacturing, construction and distribution industries. In 2013, she began a consulting practice providing contract CFO services to companies, one of which was XRG and joined XRG as CFO in 2019. Gina has always enjoyed working in the small business arena, helping business owners to profitably grow and manage their businesses.